GALLOWAY
STATION TIE-IN.

A 42" high-pressure crude tie-in across rural Kansas. 78 miles delivered 12 days ahead of schedule, zero recordable incidents over 78,000 work hours.

PROJECT OVERVIEW

WHAT WE DELIVERED.

In Q1 2022 a major midstream operator engaged PCM to deliver a 78-mile mainline tie-in connecting two existing pipeline corridors through rural Kansas. The scope included new 42" mainline, multiple highway crossings, hydrostatic testing, and full commissioning into both operator-controlled stations.

PCM ran two construction spreads in parallel, one east of Galloway and one west. They met in the middle on day 41. Welding production rates ran 12% above plan thanks to weld-quality continuity from a single PCM team across the full corridor.

  • 42" Diameter Mainline
  • 78 Miles Total Length
  • 78,000 Work Hours
  • 0 Recordable Incidents
  • 12 Days Ahead of Schedule
  • Plains, KS
RESULTS

WHAT THE NUMBERS SAY.

42"
MAINLINE
78mi
LENGTH
0
INCIDENTS
-12d
VS. SCHEDULE